Since the existing facility did not exist or detailed project documentation, individual constructive elements were identified only after excavation, and subsequent research and tests, the University of Tuzla, established a real state of reinforced concrete structure and defines the necessary rehabilitation measures.
As part of the information, it is pointed out that the physical and mechanical characteristics of built-in materials meet the required standards, but that the observed differences and design regulations (Eurocode), additional reinforcements of the structure need to be implemented. All activities take place with the supervision of professional institutions and the supervisory authority, and solutions will be defined through the amendment of the main project.
“We have created the assumptions that the dynamics needed back. We will meet the heads of all actors and contractors, the project, and in order to remove all concerns and to return the necessary dynamics,” Irfan Halilagić, Prime Minister TK.
Halilagic denied the allegations of opposition parties from TK, which in the statements emphasized that the contractor was paid more than 10 million marks, without not even beginning.
“The contractual value of the works is 11,245,000 KM with VAT, 416,763 KM has been implemented so far. We may have been paid to such allegations, but here we have been waiting for all the answers. If we come to the situation to choose between Losing time on the one hand and safety and quality of the object, we will re-choose the other. We want an object that will be safe, representative and done in accordance with the project and which will be served for which it is intended, “Halilagić said.
The public procurement procedure for the selection of contractors and the supervisory authority was conducted in accordance with the Law on Public Procurement of Bosnia and Herzegovina, and the public is properly informed about each phase of the process. “Jokić-Invest” doo Zvornik, and for construction supervision services, the Institute of Construction Ig Ltd. Banja Luka were selected for the contractor.
“In the coming period, the” Rule of Tuzla Canton will continue to transparently informing the reconstruction of the government’s building and functional space, but invariably fail to pay untrue information and not to deceive the public with their unfounded steps, “said the Vlade of the TC.