For the second time, the tender for providing supervision service on the construction of the Osimice Supplement – the prices on Corridor 5C is canceled.
The notice was on Wednesday 28. May published by the EU Delegation to BiH. Namely as it is stated in it 15. October 2024. The Tender for submission of bids without pre-qualification, for the provision of consulting services for the construction of the caretor 5c highway, a subdivision of about 12 km long. Services related to the supervision and administration of the contract on works, quality control, as well as reporting in accordance with the provisions of the basic works to be performed according to FIDIC 1999 GCC for the employer design works. The procedure was open to firms and joint ventures from all countries.
In January 2025. Four companies submitted their technical and financial bids in accordance with the requirements set out in the Agreement. The proposals were supposed to be evaluated on the basis of the most economically most favorable offer. The validity period of all offers has expired 13. May 2025. years. The contracting authority (FBiH highway) interrupted 15. May 2025. By informing all the bidders, it is in the information on the interruption of the proceedings.
The deadline for the execution of works was 24 months, and the concrete reason why the FBiH motorways annulled the tender was not published.
Recall the estimated value of the job was EUR 4.7 million without VAT and its financing the European Investment Bank (EIB). The original deadline for receipt of the bid was 30. December 2024, but it was subsequently extended until 13. January 2025.
The eKapija portal was also written that the first announced international tender for the construction of winter oversight is the construction of the Corridor VC Medakovo, and that no one was elected winner.
It is an epilogue of events, after the tender was announced in May 2022. year, and the value of which is estimated at EUR 4.7 million, and the duration of the job is provided for in 48 months.
The latest events and annulment of another tender further complicate the construction of this subdion, which is why the giving of any assessment of the possible beginning of the work is reduced to mere guess.
At the stakeholder, the construction of nine bridges is envisaged in the total length of 4,333 meters, and higher and more demanding facilities are designed through the riverbeds of Bosnia, main road and railway. The route also includes the construction of five tunnels with a total length of 5,677 meters.
Construction and lack of money
Last October from the FBiH Highway, it was that the process of evaluating the contractor in the final phase and the contractor of the contractor with the International Creditor, which is the beginning of the last quarter of 2024. The beginning of construction is planned by the end of 2024. Years.
But the latest information show a different picture.
Namely, a month ago, the FBiH government accepted the information “regarding the missing funds for the construction of the highway on Corridor 5C shares Medakovo – pretrikes, subdivisions – spaced”.
– aware of the growth of prices The Government of the Federation of BiH shows the commitment to the implementation of the strategic project to the Corridor 5C shares, and in cooperation with creditors in the coming fundres, it is said from the Government, writing eKapija.