Works on the construction of the Motorway Corridor 5C through the Zenica-Doboj Canton take place intensively to several key shares. The special focus is on the Medakovo – Osimice section, where significant works on the breaking tunnel of the black top of 2.2 kilometers in length, building more bridges, viaducts and routes.
This section, which passes through the municipalities of Tešanj, Maglaj and Žepče, is the longest and the most expensive contractual shares on Corridor 5C in Bosnia and Herzegovina, with a value of over 420 million euros with VAT.
At the Nemilian Stock – Vranduk, 5.67 kilometers long, the works are progressing well. Works are currently being performed on the construction of retaining pillars for bridges related to the viaduct above the main road M-17 and is also operated on the construction of the route. This stock is significant because the shares will merge – unemployed in the north and vranduk – annulment in the south, allowing continuous traffic to this part of Corridor 5c.
In the section, Nemils are in progress, paving parts of the route, as well as the construction of the facilities of the internal transport system and rest areas. It is planned that this holiday is available with both highway directions, providing drivers of the necessary facilities and services.
The construction of the toll house is also taken place at the Traveler’s hill – Medakovo, while the rest of the route is being built, which will be connected to the part of the highway in Republika Srpska, allowing the connection between the 9th January towards Gradiška and Banja Luka.
After a long period, the works on the stakeholders in Vranduk – Zangor, where the route work for the route and the insurance of the slopes are intensified. These works are expected to contribute to the acceleration of construction and connecting this part of the highway, transmitting Ziti.