At the moment, the general public is not known what exactly changes to the route in the length of 8.5 kilometers near this industrially developed city, writes the Biznisinfo.ba.
The Federal Ministry of Physical Planning called for amendments to the Main Project of the Motorway on Corridor 5C at the Putnikova brdo – Karusha and Karushi – Medakovo, 7.5 km long.
Only the parties in the process of adopting a decision on granting the amended part of the main project for the construction of the Putnikovo brdo – Medakovo, which means there is no insight into what specifically changed.
It is about 8.5 km long route, in the municipality of Doboj South, Usor and Tešanj in Zenica-Doboj Canton. Parties in the procedure may inspect the main project in the premises of the Federal Ministry of Physical Planning.
The project investor is the public company of the FBiH motorway, and the works on this section are performed by the Sarajevo company Euro-Asphalt. The contract on the construction of this section was signed on 11. November 2022. years and the value of contracted works is 167 million euros with VAT.
The construction deadline was 24 months, which means that it has expired, and it is obvious that the project is neither close to finalization.
By the way, Biznisinfo.ba wrote a few days ago that the Tešanjka River will be mixed in this section due to the construction of the highway.
As we wrote, that this relocation of the river will not be just simple that this is a great project, the fact that it will cover as many as 50 real estate mostly categorized as the fields of which several hundred squares.
About Stakeholders Putnikovo Brdo – Medakovo
The start of the route is at the exit of the Tunnel, Putnikovo brdo 2 on the inter-entity line. Further route is provided according to the loop of the Usor where the lateral toll site is located after which the route crosses the bridge over the regulated trough of the River Usor and the Karusha settlement reaches the village.
In the carousine, the route passes through the hill and at that location the Cut & Cover system in the length of 220 meters. Below the route passes through the settlements of Tešanjka and Medakovo as well as uninhabited areas.
The stock ends after the loop of Medakovo.