Saga About the disputable procurement of a linear accelerator at the UKC Tuzla has not yet been completed

Crime3 min čitanja
Saga About the disputable procurement of a linear accelerator at the UKC Tuzla has not yet been completed

Saga on the disputable procurement of the linear accelerator at the University Clinical Center Tuzla has not yet been completed.

We remind you, the Clinical Center procured a linear accelerator with the accompanying equipment from Mostar Inelmed at the end of last year. Value – eight and a half million marks. However, the Court of BiH respected the company “MSG” from Tuzla, which the competent public procurement commission has disqualified from the tender procedure, and returned the UKC to re-treatment. This practically means that the Tuzla Clinical Center must accept proof of payment of the appeal procedure and thus the Things returned to the beginning of the tender procedure.

The Court of BiH stated that the UKC was the disputed act upon the rules of procedure because it did not properly evaluate the evidence that the UKC was obliged to adopt a new decision and implement the BiH Public Procurement Act. The UKC Management Tuzla is silent about that, and the legal representative of the company Msg Tuzla could not comment on all this. Will the decision of the Court question the Tender on the basis of which UCC Tuzla signed the contract and procured a linered accelerator and ancillary medical equipment worth eight and a half million marks, is not yet known? The government is not worried, they say that the procurement of the treatment for oncological patients could not wait.

“Of course we are here to respect the judgments of the courts, that we also respect them when it is necessary to apply them, a certain kind of pressure of that apparatus, remains to be seen,” said Irfan Halilagić, Prime Minister Tuzla Canton.

Žarko Vujović, President of the Assembly of the Tuzla Canton, said the “greatest consequences were human health, because the interests of great capital was supported by some law firms”, and how the profit was significant, and not human health. “

“And that now happens. It is important that the linear accelerator was procured,” Vujović added.

The opposition warns that in the last case, as in previous unsuccessful procedures, justified doubts about adjusting tenders and violation of the Law on Public Procurement.

“And then it was said that this was late, that there was a problem about the payment slip, so it will be apparent, and that in further steps, the law is made,” said Dževad Hadžić in the SDP club in the TC Assembly.

The Prosecutor’s Office of Tuzla Canton claim that the Tender Procedure that resulted in the signing of the contract with the INELL-honey was not covered by an investigation against the former management due to the suspicion of adjusting the tender for the procurement of the Liners Accelerator.

“The issue of certain interpretations of the validity of the public procurement procedure, which of course, could not wait for this first. In terms of the same commissions, it was not in terms of the assessed amount of public procurement and the property of the Special Department,” explained the Vedran Aližanović, Chief Prosecutor of the Prosecution of TK.

Thus, if possible, the subject of the judiciary may be decided on that, the indictment was previously forwarded to the Tuzla Husić’s former Denijal. For the abuse of the positions in the implementation of the Procurement Procurement Procurement. accompanying equipment. The indictment re-returned the indictment in the investigation phase that is not known when it will be completed.

(Type / Source: federal.ba/autor: Omer Hasanović / photo: Archive)